11 KV Line Conductor Phase to Phase Clearance / 11 KV Line Conductor to Conductor distance-
During Erection of 11 KV Line After Erected Pole , Pin insulator , Top clamp ( Single Pole ) , Disc insulator ( Line DP) work done . Then Three Phase Conductor work done ( Three Conductor used . Two Conductor in Single Pole Pin insulator groove & one Conductor erected through Top clamp pin insulator groove . Pic attached for reference given below).
Conductor. Conductor. Conductor.
Left Side Central Right Side
* Central Conductor to other two side conductor phase to Phase clearance is 650 mm.
* Left & Right Side Conductor Phase to Phase Clearance is 1070 mm.
YouTube Link given below for watch video .
https://youtu.be/TvRO7Ru0OAw
During Erection of 11 KV Line After Erected Pole , Pin insulator , Top clamp ( Single Pole ) , Disc insulator ( Line DP) work done . Then Three Phase Conductor work done ( Three Conductor used . Two Conductor in Single Pole Pin insulator groove & one Conductor erected through Top clamp pin insulator groove . Pic attached for reference given below).
Conductor. Conductor. Conductor.
Left Side Central Right Side
* Central Conductor to other two side conductor phase to Phase clearance is 650 mm.
* Left & Right Side Conductor Phase to Phase Clearance is 1070 mm.
YouTube Link given below for watch video .
https://youtu.be/TvRO7Ru0OAw
No comments:
Post a Comment