11 KV Line Single Pole Erection work with material Details.

11 KV Line Single Pole  Erection work necessary Process follow for Erection of 11 KV Line Single Pole .
1- After Survey Done  ,BOQ Prepartion  & Approval  BOQ of Particular Village, Habitation, Feeder Separation, Feeder Bifurcation  Then work Started Particular Locations.
2- For Erection of 11 KV Line Pole is necessary part.
3- Rural Project for 11 KV Line- 8 mtr(140 kg) Long PCC Pole used.
 - Urban Project for 11 KV Line - 11 mtr(37.1 kg/mtr)  H-Beam Pole used.
4- Tractor mounted Pole pit diggier &  Manually( By Labour) Pit digging done.
3- Pit hole done by Tractor mounted Pole pit diggier & Erected The Pole .
4- During  Erection of Pole Stone Bolder (60 % ) & Compacted Soil (40 %) fill at  Pit hole in Rural Project .
For Urban Project  Pit hole Full Concerting with Composition ( 1:3:6 Cement:sand: Aggregate)  done from Bottom of pit hole to ground level.
5- V - Cross arm & V Cross arm supporting  Back Clamp fitted in Pole work done during Erection of 11 KV Line.
6- Pole Top portion one Top Clamps done.
7- Three no. Pin insulator 5 KN done ( Two pin insulator at V - Cross arm & one pin insulator at Top Clamps).
Note - Some urban  project no Top clamp used.
8- one no. Earthing Coil done.
9- Earthing for PCC Pole done as per approval.
10- Barbed wire (3.5 kg 12 SWG or 14 SWG GI Wire used as per approval).
11- Danger Board of 11 KV uesd in pole for indicate 11 KV Line Erected & it is Danger.
12- Stay Set 16 mm complete with Turn buckle work done.
13- Stay wire 5.5 Kg per pole done.
14- Stay Pit digging & Concerting work necessary for Erection Stay set with Stay wire.
15- Galvanised Nut, Bolt & Washer used.


https://youtu.be/tybhC1Caj5c